Roswell will mark the start of its $10.7 million Riverside Road improvement project with a groundbreaking ceremony Tuesday, Nov. 17, at 1 p.m.
According to the city’s announcement on X, the ceremony will take place between Ace Sand and St. Andrews Church. Parking will be available at Ace Sand, 705 Riverside Road.
The project covers approximately two miles between Riviera Road and Old Alabama Road. In its project update, the city outlines a roundabout at River Lake Drive, a new traffic signal at Taimen Drive, raised medians, bicycle lanes, sidewalks, pedestrian crossings and drainage improvements.
The plans also include an 8- to 10-foot multiuse trail on the south side of Riverside Road and a 5-foot sidewalk on the north side.
According to council records, the board approved a $9,489,436.50 construction contract with BackBone Infrastructure, LLC, on July 13. Total project authorization is $10,721,901.50.
Funding includes $9,267,321.50 from Roswell’s TSPLOST 2 fund and $1,454,580 for associated Fulton County waterline work. County records show commissioners approved the waterline agreement Sept. 2.
Drivers should expect periodic lane closures, temporary traffic shifts and active work zones during construction. The city says access to neighborhoods, businesses, schools and parks will be maintained whenever possible.
Tree removal is another part of the work. The city reports that 129 trees will be removed and 49 new trees planted. Those removals include 23 of the corridor’s 95 specimen trees, leaving 72—approximately 76%—in place.
The city says engineers evaluated alternatives to preserve existing trees while making room for transportation improvements, drainage and utilities.
Residents can follow construction milestones and traffic advisories through Roswell Connections and the city’s social media channels.